Most companies that design AI chips do not own a fab. They send the design to a foundry - a contract manufacturer - where the chip is made and also assembled with its memory. This link is highly concentrated. At its head is Taiwan's TSMC, which brought in $122 billion in 2025, 58% of it from high-performance computing. Just ten customers accounted for about 78% of its revenue.
Errors or inaccuracies are possible. Spotted something that looks wrong? Write to me and I will correct it.
Two steps, one link
Wafer manufacturing. The foundry receives a design file from the customer and prints it onto silicon wafers, in dozens of layers, using the lithography, etch and inspection equipment described in the research on chipmaking equipment. The technology is measured in nanometers: how small the features are, and so how many transistors fit on a chip.
Advanced packaging. Packaging used to be a relatively simple step: encase the chip and connect it to a board. In AI accelerators it has become a manufacturing step in its own right. The large processor is placed on a silicon interposer, with stacks of HBM memory beside it, so data moves between them over a wide channel and a short distance. At TSMC these services are called CoWoS and SoIC, which is how it describes them in its annual report. They are meant to deliver high compute density, energy efficiency and low latency.
Independent packaging and test companies also work in this link, as do chipmakers developing their own packaging, such as Intel and Samsung.
How the money flows
On paper the model is simple. The designer - Nvidia, AMD, Broadcom, Apple, or a cloud giant designing its own chip - pays the foundry for every processed wafer and for packaging services. The foundry carries the factory risk: it invests tens of billions of dollars a year in capacity and earns it back through utilization and price per wafer.
That is why the two most important numbers here are the capital budget and the revenue mix.
| TSMC | |
|---|---|
| 2025 revenue | NT$3.81 trillion ($122 billion according to the company) |
| Growth | 31.6% in NT dollars, 35.9% in US dollars |
| HPC share | 58% (51% in 2024) |
| 2025 capital spending | $40.9 billion |
| 2026 capital budget | $52-56 billion |
| 2026 revenue growth outlook (January) | close to 30% in US-dollar terms |
The HPC line is where AI accelerators appear, and in one year it rose from about half of revenue to close to sixty percent. On the customer side, Nvidia reported $107.6 billion of data-center revenue in the quarter ended October 25, 2026.
Where the bottleneck is
- Packaging, not only wafers. Even with enough wafers, every accelerator needs a slot on the advanced-packaging line. TSMC writes in its annual report that it is expanding this capacity, but does not publish a capacity figure. Numbers in the market are outside estimates, so none appear here.
- Customer concentration. According to the annual report, TSMC's ten largest customers accounted for about 70% of revenue in 2023, about 76% in 2024 and about 78% in 2025. The largest customer alone was 25%, 22% and 19% respectively. The dependence runs both ways: a few designers, and one manufacturer nearly all of them need.
- Geography. Most advanced capacity sits in Taiwan. TSMC also operates a fab in Arizona (Fab 21) and in Kumamoto, Japan (Fab 23), and older fabs in China and Washington State.
- Build time. TSMC's annual capacity exceeded 17 million wafers in 2025 (in 12-inch equivalents), against about 17 million in 2024. According to the company, the increase came mainly from expanding 3-nanometer. A new fab takes years, so annual additions are limited.
What pushes it forward
- Demand comes from several directions. General accelerator designers and cloud giants designing their own chips build in the same fabs.
- Every generation needs more. A new accelerator is larger, needs more memory and relies more on advanced packaging, so the value of work per accelerator rises.
- A growing capital budget: $52-56 billion in 2026, against $40.9 billion in 2025.
What could stop it
- The customers' investment cycle. A foundry's revenue depends on how fast the cloud giants buy servers. A slowdown there arrives here a few quarters later.
- Concentration. A large customer that changes an order, or moves part of its production to a rival, moves the numbers.
- Geopolitics. The concentration of production in Taiwan, and trade restrictions between the US and China, are risks the company itself describes in its annual report.
- The cost of spreading out. Fabs outside Taiwan spread the geographic risk, and TSMC writes that higher costs in the US may reduce its profitability.
The optimistic reading does not explain what happens to utilization if the cloud giants' investment eases. The cautious reading does not explain why the company is raising its capital budget by tens of percent in a single year.
Company map for this link
Factual mentions only. This is not a closed list and not a recommendation.
| Sub-link | Companies | Role |
|---|---|---|
| Advanced foundry | TSMC, Samsung Foundry, Intel Foundry | Contract wafer manufacturing |
| Advanced packaging | TSMC (CoWoS, SoIC), independent packaging and test companies | Assembling processor and memory on one substrate |
| Designers (the customers) | Nvidia, AMD, Broadcom, Apple, cloud giants | Pay for wafers and packaging |
| Memory for packaging | SK hynix, Samsung, Micron | Suppliers of HBM stacks |
Further reading
- AI capex of the cloud giants: where the money flows in the chain - the master article of the compute and AI chain.
- Lithography and chipmaking equipment - what the foundry buys.
- HBM memory - what is assembled beside the processor.
Sources
TSMC: 2025 annual report (20-F), Q4 2025 earnings call (15.1.2026). Nvidia: Q3 fiscal 2027 results release (17.11.2026).
Ilan Abramov, the author, or anyone on his behalf may hold securities mentioned in this article, and holdings change from time to time.