At the end of 2025 Israel had 8,159 MW of installed renewable capacity, 30.9% of all capacity in the system, yet renewables supplied only 16.7% of electricity consumption. The government target is 30% by 2030. In 2026 the Ministry of Energy published two drafts for public comment, a national renewables plan and a storage policy, and both present the grid as the main constraint. Meanwhile the Electricity Authority expects storage capacity to grow from 557 MW in 2024 to about 9,250 MW in 2030.
Errors or inaccuracies are possible. Spotted something that looks wrong? Write to me and I will correct it.
Why it matters
The Electricity Authority does not publish the sector's weight in GDP. What it does publish is the sector's share of the electricity system, and that share has risen quickly over the past decade:
- Capacity: from 870 MW in 2016 to 8,159 MW at the end of 2025, according to the Electricity Authority's status report. About 1,300 MW of facilities were connected in 2025.
- Consumption: the actual share of consumption from renewables rose from 5.0% in 2019 to 16.7% in 2025. The amount consumed rose by about 15.6% in 2025 compared with 2024. Another measure the Authority publishes, "consumption potential" based on installed capacity at year-end, stood at 18.8%.
- Generation: according to Noga, the system operator, renewables reached 15.3% of generation in 2025.
- Hours of the day: in 2024 more than 30% of electricity generated between 10:00 and 15:00 came from renewables, and in some hours more than half of all generation did.
In its draft storage policy the Ministry of Energy writes that because most renewable generation is solar, a gap has opened between generation hours and demand hours, and that storage makes it possible to bridge it.
How the sector works
The sector rests almost entirely on the sun: in November 2025 solar (PV) was about 92% of renewable capacity, according to Electricity Authority data cited in the draft national plan. Wind was 343 MW and solar thermal 242 MW.
| Segment | Capacity, November 2025 | Facilities | What it includes |
|---|---|---|---|
| Dual-use | 4,316 MW | 63,687 | Residential rooftops, commercial and industrial rooftops, canopies and water infrastructure |
| Ground-mounted | 3,033 MW | 369 | Plants on agricultural cooperative land, joint ventures and large plants, including solar-plus-storage |
| Agrivoltaic | In planning | - | Panels above active farmland |
Within dual-use, 58% of capacity (2,479 MW) sits on non-residential rooftops and canopies of 15 to 200 kW. Residential rooftops of up to 15 kW account for 35,810 facilities but only 698 MW.
How the price is set. Small facilities connect under regulations in which the Electricity Authority sets a fixed tariff for many years. Large facilities compete in competitive processes for a tariff, or sell power to private suppliers under the market model. According to the Electricity Authority, the average nominal tariff for dual-use facilities connected between January and June 2025 was 35.0 agorot per kWh, and 20.2 agorot for ground-mounted plants. In 2009 the dual-use tariff was 248.0 agorot. The Authority attributes the 2025 decline to a larger share of capacity coming from competitive processes rather than regulated tariffs.
Who pays. The cost passes to consumers through the electricity tariff. According to the Electricity Authority, the average cost of buying power from renewable facilities was expected to be about 51 agorot per kWh in 2025. For comparison, the average cost of buying from private conventional producers was shown at about 36 agorot, and the Authority notes that this is not the alternative price against which excess cost is calculated. In a hearing dated 18 October 2026 the Authority estimated that the excess cost of the low-voltage regulation, compared with conventional generation, is about NIS 150-180 million a year, assuming the volume and mix of connections stay similar to those of the past 12 months.
Storage. According to the Ministry of Energy, the Electricity Authority's storage regulations are divided by voltage level: competitive processes and a bilateral market at extra-high voltage, a market model with quotas that Noga allocates to each area at high voltage, and at low voltage a complementary tariff for those who store power and feed it into the grid during demand hours. Under the bilateral model on the transmission grid, Noga decides when facilities charge and discharge.
The players
- The Electricity Authority sets tariffs, regulations and competitive processes, and publishes the annual status report.
- The Ministry of Energy sets policy. In 2026 it published two drafts for public comment: the national renewables plan for 2035 (May) and the storage policy (November).
- Noga operates the system. According to its sustainability report, by the end of 2025 it had integrated 19 renewable plants into the extra-high-voltage grid with a combined capacity of about 1,075 MW. In 2025, 77% of renewable generation was on the distribution grid and 23% on the transmission grid.
- The Israel Electric Corporation (IEC) owns the grid and connects most facilities. According to the draft storage policy, the distribution grid development plan approved in November 2024 aims for about 3,600 MW of storage on the grid by 2030, and IEC's market share in storage is capped at 15% of the private market share.
- The Israel Land Authority allocates land. According to the Ministry of Energy draft, in June 2024 it cut the uniform price for allocating land to standalone storage facilities from NIS 70,000 to NIS 30,000 per installed MWh.
- Developers. The first competitive process for extra-high-voltage storage allocated 1,500 MW in three regions, with a cap of 150 MW per facility. According to the Ministry of Energy, six developers won 11 facilities due to be built in 2028 and to operate under the tariff until 2043. One of them is an Enlight facility at Ne'ot Smadar with a capacity of 150 MW, according to Electricity Authority decision 74302.
- Enlight, which is also listed on Nasdaq, reports to the US Securities and Exchange Commission in its third-quarter report (3 November 2026) that about 25% of its operating portfolio, which the company puts at 4.0 GW in its own terms, was in Israel. In Israel it had projects of about 370 MW under construction, including the Ohad high-voltage storage facility (193 MW), and a further 572 MW or so at the pre-construction stage. The company also reported revenues of about $56 million in the third quarter of 2026 from electricity trading in Israel, and 40% of trading revenues in the first nine months came from power generated at its own projects.
Growth drivers
- Storage: according to the Electricity Authority, there were 557 MW of storage in the system in 2024. For 2030 it forecasts about 9,250 MW: 4,950 MW standalone, 3,500 MW at solar plants with storage and 800 MW of pumped storage, with a capacity of about 40,200 MWh. The forecast is based on grid-connection responses and connection surveys. In February 2025 the Kochav HaYarden pumped-storage facility (344 MW) was connected, alongside the Gilboa facility (300 MW), and according to the Ministry of Energy another facility is expected at Manara.
- Demand for quotas: the Ministry of Energy describes "unprecedented demand" for storage, reflected in quotas filling quickly. Under the bilateral model on the transmission grid, quotas of 2,000 MW for paired facilities and 600 MW for standalone storage were set, and because of heavy excess demand a lottery was set for connection surveys.
- Agrivoltaics: in February 2026 the government approved a dedicated national outline plan (TAMA 24/1) for agrivoltaic facilities. According to the Ministry of Energy, in April 2026 there were 23 approved plans and 36 in process, covering about 16,000 dunams with an estimated capacity of about 1,230 MW.
- Large plants: according to the Ministry of Energy, tenders have been published for ground-mounted plants of more than 100 MW, and initiatives for very large plants are being examined, for example in the Oron-Zin area.
- Falling costs: in the October 2026 hearing the Electricity Authority wrote that solar installation costs have fallen, and proposed cutting low-voltage tariffs by 5% each year until 2030. The draft national plan estimates that most capacity added by 2035 is expected to be built under a competitive model, without subsidy.
Challenges and risks
- The target: government decision 465 of 2020 set 30% by 2030 and an interim target of 20% for 2025. In 2025 the consumption share was 16.7%. According to the Electricity Authority's estimate, as cited in the draft national plan, on current trends the target will be reached about two years late. The draft also notes that the government decision uses generation and consumption terms interchangeably.
- The grid: the Ministry of Energy draft describes grid capacity as "the main bottleneck". About 75% of solar capacity is installed in the south (50%) and north (25%), and 85% of ground-mounted capacity is in the south, while demand centres are in the centre of the country. The draft describes a high rate of negative or partial responses to connection requests.
- Curtailment: Noga limits output at extra-high-voltage solar facilities during peak sun hours to keep the system stable. A quantitative figure for the amount of energy curtailed was not found in the official documents reviewed. The transmission grid development plan prioritises storage in the areas with the highest curtailment rates: the western Negev, the Arava and Eilat.
- Land: in 2020 the National Planning and Building Council set a quota of 60,000 dunams for ground-mounted solar plants until 2030. In the draft national plan the Ministry of Energy writes that the quota is not expected to meet needs after 2035, and that where the grid is available there is usually no free land, and vice versa.
- Slow agrivoltaics: according to the Ministry of Energy, about 140 projects won support as agrivoltaic pilots, but only 8 were actually built, partly because of delays in grid connection and lack of economic viability.
- Fire safety and regulation in storage: in a Ministry of Energy survey of 17 developers, regulatory complexity was ranked the most significant barrier (29% of the weight of barriers), followed by economic uncertainty (23%) and grid connection times (22%). The ministry describes fire-safety requirements as the main bottleneck in building facilities, partly because new editions of the US standard (NFPA 855) are adopted automatically.
- Grid management: in July 2026 the Electricity Authority decided that the distribution operator may shift the charging and discharging hours of storage facilities under the distribution market model, and may limit charging for up to 100 hours a year without compensation. Large-scale real-time management will not be possible before 1 January 2028.
- Dependence on the sun: the draft national plan notes that Israel relies almost entirely on solar generation, and that government spending on energy R&D is about 0.7% of government R&D spending, compared with an OECD average of 3.4%.
Draft national plan for 2035 (May 2026, for public comment)
| Component | Capacity |
|---|---|
| Existing (end of 2025) | About 8 GW |
| Under construction | About 4 GW |
| Required addition: agrivoltaic | About 5 GW |
| Required addition: ground-mounted | About 4.5 GW |
| Required addition: dual-use | About 4 GW |
| Required addition: other technologies | About 0.5 GW |
| Capacity target for 2035 | About 26 GW |
According to the Electricity Authority, a target of 35% of generation in 2035 would require about 22 GW, and a 40% target about 26 GW. This is a draft, and the 2035 target has not yet been finally set.
What to watch
- The 2035 target: in the November 2026 draft storage policy the Ministry of Energy writes that the state is still "examining" targets of 35% to 40% for 2035. Will the target be set, and when, and will it be anchored in a government decision with targets by segment, as the May 2026 draft national plan proposes?
- The storage strategy: the November 2026 draft proposes moving from ad hoc quotas to quantitative targets by voltage level and region, and setting up a dedicated team to remove barriers. What will remain in the final version?
- 1 January 2027: under the October 2026 hearing, the updated low-voltage regulation is meant to apply from this date, with a uniform tariff period to the end of 2047 and a new market-model-plus-premium track. This is a proposal in a hearing, not a final decision. The complementary tariff for low-voltage storage (criteria 175 and 176) is in force until the end of 2026.
- The storage chapter of the national outline plan: amendment no. 2 to the storage chapter was brought to the National Planning and Building Council on 6 October 2026, to be passed on for comments from the district committees and the public. Among other things, it proposes defining a large facility by energy content of up to 140 MWh.
- The next status report: according to the Ministry of Energy, the Electricity Authority's storage forecast is expected to be updated with the electricity sector report in the last quarter of 2026.
- 2028: the storage facilities from the first extra-high-voltage competitive process are due to be built this year. Large-scale real-time management of storage facilities on the distribution grid will not be possible before 1 January 2028.
The broader background on the electricity sector, the reform and the tariff is covered in the article on Israel's electricity sector.
This article describes the situation and official data only. It is not investment advice and not a recommendation to take any action.