Hut 8 reported third-quarter 2026 results on Wednesday, November 4, before the open, and held its investor call at 8:30 a.m. Eastern. Revenue fell 14.9% to $71.1 million, and net income rose to $189.5 million, but $413.8 million of that is a gain on revaluing digital assets. Alongside this, the company signed a second 352 MW lease at the Beacon Point campus, and the stock closed down 23.23% on the report day.
Errors or inaccuracies are possible. Spotted something that looks wrong? Write to me and I will correct it.
What was reported
| Q3 2026 | Q3 2025 | Change | |
|---|---|---|---|
| Revenue ($ millions) | 71.1 | 83.5 | -14.9% |
| ← Power | 1.3 | 8.4 | -85.0% |
| ← Digital infrastructure | 1.4 | 5.1 | -72.9% |
| ← Compute | 68.4 | 70.0 | -2.3% |
| General and administrative expenses | 99.6 | 25.9 | 3.9x |
| Gain on digital assets | 413.8 | 76.6 | 5.4x |
| Operating income | 318.2 | 72.7 | 4.4x |
| Interest expense | 105.5 | 8.6 | 12.2x |
| Net income | 189.5 | 50.6 | +274.4% |
| Adjusted EBITDA | 33.0 | 30.5 | +8.3% |
| Adjusted EBITDA including bitcoin revaluation | 350.3 | 109.0 | 3.2x |
Source: Hut 8's press release of November 4, 2026, filed with the SEC on Form 8-K as Exhibit 99.1, and the quarterly 10-Q. "Adjusted" is a non-GAAP measure; since the second quarter the company strips the revaluation of its own bitcoin out of adjusted EBITDA. Changes are calculated from the release data. All figures in $ millions.
Power and digital infrastructure revenue fell because of the sale of the Far North partnership in February 2026 and the end of the hosting agreement at the Vega site in August 2025, and compute revenue slipped even though the number of bitcoin mined rose to 891 from 578, because average revenue per bitcoin fell to about $71 thousand from about $114 thousand. Compute gross margin, before depreciation, fell to 59.0% from 68.5%. The company also sold its traditional cloud business in August.
The asterisk: bitcoin revaluation
Operating income of $318.2 million includes a $413.8 million gain on revaluing digital assets, mostly unrealized. The reason: the price of bitcoin rose during the quarter from about $59.8 thousand to about $83.4 thousand. Without this item operating income is negative, about $95.6 million. And the quarter's net income hides a wider picture: since the start of the year the company has posted a net loss of $240.8 million, meaning the first two quarters together came to a loss of about $430 million.
Below the line, several material items:
- General and administrative expenses of $99.6 million versus $25.9 million: $58.4 million of the increase is stock-based compensation, mainly one-time grants from 2025, and $7.7 million is professional fees, mostly legal.
- Interest expense of $105.5 million versus $8.6 million, following the project bonds. Interest income of $61.8 million, from investing proceeds not yet spent, offset part of it.
- A loss of $62.8 million on revaluing bitcoin redemption rights tied to American Bitcoin's purchase of mining machines, against a $23.7 million gain on revaluing the investment in Ionic.
Adjusted EBITDA, excluding bitcoin revaluation, is $33.0 million versus $30.5 million a year earlier: an increase of only 8.3%, and a small figure next to interest expense of $105.5 million.
The contracts, the financing and the timetable
The material thing in the quarter is the contracts. The second lease at Beacon Point, 352 MW of IT capacity, is worth about $9.8 billion over the base term and about $655 million of expected average annual net operating income, on a triple-net, take-or-pay basis. The whole campus, both phases, is fully leased, at a contract value of about $19.6 billion and net operating income of about $1.3 billion a year. The expected contract value across the entire data center portfolio: about $26.6 billion.
| Campus | Utility capacity under construction (MW) | First data hall | Financing |
|---|---|---|---|
| River Bend | 330 | Q2 2027 | $3.25 billion notes, 6.192%, 2042 |
| Beacon Point Phase 1 | 500 | Q3 2027 | $4.25 billion notes, 6.129%, 2042 |
| Beacon Point Phase 2 | 500 | Q2 2028 | Not yet closed |
Source: Hut 8's press release of November 4, 2026 and the 10-Q. The River Bend and Beacon Point notes were issued in April and June 2026 by the project companies and are not guaranteed by the parent.
At River Bend the tenant is Fluidstack, and Google provides a financial backstop for the rent payments. At Beacon Point the tenant is described in the 10-Q as a high-investment-grade company, and is not named. Both bonds are secured by liens on the project assets, and much of the money raised has not yet been spent: $3.56 billion of restricted cash and $2.84 billion of restricted short-term investments, about $6.4 billion together, against $157 million of unrestricted cash. Construction progress: at River Bend, structural steel and foundations were completed across all four data halls and the substation was energized; at Beacon Point, construction of the substation began.
Management says the projects will be funded at the project level only, with no equity issuance and no recourse debt at the parent. Phase 2 at Beacon Point is already counted in capacity under construction, but its financing is still being evaluated: the company writes that it is advancing financing plans and weighing various structures.
Balance sheet and capital returns
Total assets rose to $10.33 billion from $2.75 billion at the end of 2025, and financial debt (loans, notes and financial liabilities) to $7.63 billion from $0.41 billion. Equity attributable to shareholders is $1.56 billion. In addition, as of September 30 the company holds bitcoin worth $697.4 million, and another $702.9 million at American Bitcoin, plus an undrawn four-year revolving credit facility of $1.07 billion.
Buybacks: in the quarter 953,802 shares were bought for $74.7 million, about $78.3 per share, and right after it another 2,384,677 shares for $175.3 million, about $73.5 per share. Both were funded by selling about 954 and 2,148 bitcoin. In total 3,338,479 shares were bought for $250 million, and the authorization, approved on November 2, was raised to $1.0 billion.
The development pipeline
The development pipeline totals about 7,859 MW: 3,300 under diligence, 3,180 under exclusivity, 49 in development and 1,330 under construction. Capacity under exclusivity rose by 1,300 MW. The company also signed definitive agreements to buy two energized sites in West Texas, up to 230 MW, in a bankruptcy sale of Poolin-related companies, for up to $180 million, subject to power approvals. Closing is expected as early as the fourth quarter.
The two sides of the debate
The positive reading rests on the large campus being fully leased: long-term take-or-pay contracts, a bond serviced from rental income and not guaranteed by the parent, Google's backstop at River Bend, and financing that has already landed as restricted cash. On this reading, the current operating loss is construction cost before revenue begins, not a permanent state.
The negative reading points to the gap between the portfolio and revenue. Revenue fell to $71 million, lease revenue will not start before the second quarter of 2027, and general expenses and interest, gross, already reach $205 million in the quarter. Financial debt is 4.9 times the equity attributable to shareholders. Phase 2 financing is not closed, the Beacon Point tenant is unknown, and operating income currently depends on bitcoin revaluation: the bitcoin held by the company and American Bitcoin is worth $1.4 billion. And: the post-quarter buybacks were made at an average of about $73.5 per share, and on November 4 the stock closed at $48.94.
The stock
The report came before the open on November 4, so the trading reaction is the same day. The stock closed at $48.94, down 23.23% from $63.75, on volume of 13.8 million shares versus 9.3 million the day before. During the day it ranged between $48.48 and $56.98.
The whole decline cannot be attributed to the report: Cipher Digital, which reported two days earlier, fell 19.95% the same day, and in the two prior days the two stocks moved together, down 7.4% and then up 15.9% for Hut 8, and down 5.9% and then up 18.4% for Cipher.
What will decide it
- Delivery of the first data hall at River Bend in the second quarter of 2027. This is the first commitment to a tenant and lenders, and until then lease revenue is zero.
- Financing for Phase 2 at Beacon Point. Whether it closes at the project level, as management says, and at what interest rate.
- General expenses and stock-based compensation. Whether $99.6 million in a quarter is a steady level or a one-time peak.
- Bitcoin sensitivity. Every change in price moves reported operating income, regardless of activity.
- Completion of the Texas site purchase and securing power approvals for the 230 MW.